4 contractors blacklisted, salary of one of the officials stopped
Suhail Dar
DC Anantnag, Dr. Piyush Singla reviewed the execution of works under District CAPEX and Back to Village plans here at Dak Bungalow today. The implementation of works by Rural Development and KPDCL were reviewed.
SE KPDCL Anantnag informed the chair that 311 works have been authorised under District CAPEX plan of which more than 96% have been tendered and works are under execution as per timeline. 92% of the works taken up under the ‘Back to Village’ program have also been tendered.
buy priligy online blackmenheal.org/wp-content/languages/new/noprescription/priligy-no-prescription.html no prescription
ACD Anantnag informed the chair that a total of 1925 works are being executed by the department under CAPEX plan. Out of these more than 75% of work has already been tendered. Most of these works are already under execution and shall be completed as per the projected timeline. He also informed the chair that under the ‘Back to village’ program out of 850 works, more than 85% have been put to tenders. Work is under execution on most of these projects and 145 works have already been completed.
There was threadbare blockwise discussion on execution of works. Dr. Singla blacklisted 4 contractors for unnecessary delay in execution of works and wasting public resources. Further, the salary of one of the officials was also stopped on grounds of inefficiency and non-performance. The DC warned of stern action against any official whose disbursal of work is inefficient.
The Deputy Commissioner, while reviewing the execution status of works in detail, directed the officials from both departments to ensure strict action under rules is initiated against any contractors unnecessarily delaying the execution of works. He further said that timely completion of works under their supervision are key parameters for performance assessment of officers and defaults in this regard won’t be tolerated. He laid emphasis on timely expenditure of funds that have been earmarked for these plans. He further stressed on inter-departmental coordination for execution of works and any hindrances on this account must be brought to the notice of district administration.
He also directed the officials to sensitize their staff and masses regarding the importance and benefits of the planned works. He emphasized their role in addressing any local issues in implementation of these works.
The meeting was attended by ADDC, CPO, XEN KPDCL, XEN REW, BDOs, AEs, and other officials of RDD and KPDCL among others.